A comment
They built a frame house 8.5 x 9 m in size. As a foundation, 26 piles of 108 mm diameter were installed. So, the KK soils at the construction site are heterogeneous, the depth of the piles of the bel is different from 1.5 to 2.5 m. Before concreting, they cut one level, and after pouring, round heads were installed - they were not welded. The harness was made with a simple wooden beam 150x150. The frame has additional jibs for stiffening. Inside the frame is taken up with a raised beam, And outside the plywood is full. Roofing of flexible tiles on upholstered logs. The whole problem is that the house is quite tangibly swaying especially felt on the second floor. At first, the builders claimed that this was due to the lack of cladding on the frame. But after her stuffing it only got worse.
pros
High installation speed
Insignificant cost
Minuses
Low reliability of spatial design